Skip to main content

8 Safety Handbook - Reference List

The purpose of this document is to provide an overview of the documents referenced in the Safety Handbook that are used for the development of functionally safe products within PCP R&D. Some of the guidelines, tools and templates have been created in CT-QMS and are retained within PCP R&D Processes for continued support of existing, “brownfield” safety products. This “brownfield” QMS content has been reduced by number and is expected to further reduce over time as CT-QMS guidelines, tools and templates are continued to be migrated to PCP R&D Processes solutions and older safety products reach the end of their product lifecycles.

List of References used in the Safety Handbook

The following tables contain an overview of the references listed in the Safety Handbook to provide an overview as additional information. The references [Ax] and [Cx] have been created over the lifecycle of the Safety Handbook, already at the time when the Safety Handbook was available as a printed issue. Some references have been removed since then, but are in the list for a better understanding of the continuity. Others have been replaced by PCP R&D website contents, what is visible via the corresponding links.

A) Hardware & Software Development – Quality Management System

Note: The [Ax] references below are directly referred to in this document. For the full list of HW and SW Development references refer to Quality Management System.

Ref. NoDocument IdTitleDoc kindValidity in PCP R&D ProcessesCommentPCP R&D Processes reference
[A0]3BSE035082Quality System Overview (template)templateno more valid
(CT-QMS)
The Quality System Overview is covered by the QMS website and deviations (tailoring) need to be recorded in the Quality PlanN/A (PCP R&D Processes)
[A1]3BSE038906Policy for Development Processes at PA/XA/Apolicyno more valid
(CT-QMS)
General policy document replaced by the corresponding document on the webpageProcess Governance
[A2]3BSE036666Quality Assurance (QA) in product development, descriptionguidelineno more valid
(CT-QMS)
Replaced by webpage content. Reference not used in Safety HandbookQuality
[A3]3BSE014730Structure and Management of Development Programs and Projectsguidelineno more valid
(CT-QMS)
Role descriptions are available on the PCP R&D Processes webpageRoles
[A4]2PAA105433Gate Model for Projects using CT QMSguidelineno more valid
(CT-QMS)
Integrated project management webpage with linksIntegrated Project Management
[A5]3BSE038909Test processguidelineactive for Safety developmentFor Safety related development still valid.
For PA related development the Test website is to be used.
OnePCP DMS 3BSE038909

Test
[A6]3BSE039242ABB approach to IEC 61508 2nd Ed Designguidelineactive-OnePCP DMS 3BSE039242
[A7]3BSE039245ABB approach to IEC 61508 2nd Ed Testguidelineactive-OnePCP DMS 3BSE039245
[A8]3BSE028024Checklist for reviewschecklistactive-available as a template in 'Templafy'
[A9]--N/AN/A-N/A
[A10]--N/AN/A-N/A
[A11]2PAA107467Process Change ManagementguidelineactiveNew description for PCP QMS on webpageProcess Governance
[A12]3BSE070423Security Testing GuidelineguidelineactiveNew description for PCP QMS on webpageSecurity Testing Guideline
[A13]3BSE021283Document Control Plan (template)templateactiveDocument is still valid. Use is optionalavailable as a template in 'Templafy'
[A14]3BSE021284Code Review Plan (template)templateno more valid
(CT-QMS)
Code reviews are all done either in the individual work items or as a separate code review recordN/A
[A15]3BSE038863Q & Safety Plan (template)templateno more valid
(CT-QMS)
Replaced by Quality Plan, see belowN/A
[A15]7PAA003088Quality Plan (template)templateactiveNew, replacing the Quality & Safety Plan as existed in CT-QMSavailable as a template in 'Templafy'
[A16]--N/AN/AN/AN/A
[A17]3BSE038655Static Code Analysis Guidelineguidelineactive-OnePCP DMS 3BSE038655
[A18]3BSE025114Document management for projects within Product Development and maintenanceguidelineactive- reference not used in Safety Handbook
- document is still valid, for MS Office based documents
OnePCP DMS 3BSE025114
[A19]3BSE039313_TPFNames on RACIchecklistactive-available as a template in 'Templafy'
[A20]3BSE068721Safety tool selection for… (template)templateno more valid
(CT-QMS)
New template 3BSE068721 -> 7PAA004621F (available in Templafy)N/A
[A20]7PAA004621FSafety tool selection for… (template)templateactive7PAA004621 has been approved and is valid for PCP R&D Processes. Doc ID for [A20] has changed!available as a template in 'Templafy'
[A21]OnePCP DMS 3BSE039243Terminology Documentmanualno more valid
(CT-QMS)
Glossary on webpage is covering valid items in the future. Glossary is the 'entry point' but is referencing to the 'Terminology document' as well.Glossary on webpage
[A22]3BSE052207Formal Review Process GuidelineguidelineactiveNot for user manuals and no more for Wiki pages. Review of Wiki pages via review guideline in "PCP R&D Processes" webpage.OnePCP DMS 3BSE052207

How to Edit Review and Approve Markdown
[A23]3BSE082892Configuration Change Control in ADO (Scrum)Process descriptionactiveAlready called "Configuration Change Control in Azure DevOps (Scrum)"One PCP DMS 3BSE082892
[A24]3BSE032527FPGA Verification Methodologyguidelineactive-OnePCP DMS 3BSE032527
[A25]3BSE081867Application Lifecycle Management with TFSProcess descriptionactiveValid as long as ADO server is in placeOne PCP DMS 3BSE081867
[A26]3BSE039765Baseline Plan (template)templateactive-available as a template in 'Templafy'
[A27]3BSE052347Release Preparationschecklistactive (optional)Checklist for closing a project and handing over to maintenance. List required. Optional document: Not mandatory for each project but good to have. For all project.One PCP DMS 3BSE052347
[A28]3BSE087886Impact Analysis Report (TFS and Scribe)templateactive-available as a template in 'Templafy'
[A29]3BSE070612Threat Modelingguidelineactive, but outside the safety process, covered by link to cyber security webpagePart of "Cyber Security", which is covered by link to Cyber Security Part of the website.Threat-modeling
[A30]3BSE027091Library Object GuidelineguidelineactiveProject specific guide / not to be referenced from the processes.One PCP DMS 3BSE027091
[A31]3BSE040144Developer’s Instruction for Control Technologies Code Baseswork instructionno more valid
(CT-QMS)
-N/A
[A32]3BSE019320 *System 800xA Faceplate Style Guidestyle guide /user manualactive-OnePCP DMS 3BSE019320
[A33]-WithdrawnN/AN/AN/AN/A
[A34]3BSE045438ABB Approach to avoid common cause failure in PM/SMguidelineactive-OnePCP DMS 3BSE045438
[A35]3BSE045425ABB Approach to Test of Library Typesguidelineactive-OnePCP DMS 3BSE045425
[A36]3BSE034876 *AC800M HI - Reliability and Availability ManualmanualactiveNot a reference to PFD/PFH calculation but to its results.User manual(s) available in OnePCP DMS and ABB Library (sources in Skribenta)
[A36]3BSE094064Select I/O - Reliability and Availability ManualmanualactiveNot a reference to PFD/PFH calculation but to its results.User manual(s) available in OnePCP DMS and ABB Library (sources in Skribenta)
[A37]3BSE067721ABB Approach to IEC 61508 Traceabilityguidelineactive-OnePCP DMS 3BSE067721
[A38]3BSE068757ABB Approach to IEC 61508 failure classification and probability calculations for AC800M HIguidelineactive-OnePCP DMS 3BSE068757
[A39]3BSE057386Crib - Guideline to Source Code Review ChecklistchecklistactiveThe process is described on the web page. For Safety development, the MS Word document shall be considered as well.Crib - Guideline to Source Code Review Checklist
[A40]3BSE039699Safety Validation Test ProcessProcess descriptionactiveThis is a separate activity. The goal is to embed the SVT process in the PCP R&D Test ProcessOnePCP DMS 3BSE039699
[A41]3BSE067603Branch Strategy in Team FoundationguidelineactiveHow to work with products in TFS version control.One PCP DMS 3BSE067603
[A42]3BSE054111Configuration Audits - Activity Mappingsguidelineno more valid
(CT-QMS)
-Configuration Audits
[A43]3BSE053072AC800M Control protocol development and release guidelineguidelineno more valid
(CT-QMS)
Reference not used in the Safety HandbookN/A
[A44]3BSE054108FCA Checklist and Report (template)templateno more valid
(CT-QMS)
No generic template for Functional Configuration Audit; A project specific tracking of documents by project CM used instead to fulfill the task.How-to Perform Configuration Audits
[A45]3BSE039765Baseline plan (template)templateN/Aduplicate to Ref [A26]N/A
[A46]3BSE044664How to Handle Design/Module and Low-Level Integration Tests with included Test DescriptionguidelineactiveUnit test is described in: Unit Test Overview
For Safety development the guideline 3BSE044664 in One PCP DMS needs to be observed.
Unit-Test-Overview

One PCP DMS 3BSE044664
[A47]3BSE078996ABB Approach to Code Coverage AnalysisguidelineSW/Safety active-OnePCP DMS 3BSE078996
[A48]3BSE054110PCA Checklist and Report (template)templateno more valid
(CT-QMS)
No generic template for Physical Configuration Audit; A project specific tracking of documents by project CM used instead to fulfill the task.How-to Perform Configuration Audits
[A49]3BSE086007Field Communication OverviewoverviewactiveValid for PCP R&D Processes and CT-QMSOne PCP DMS 3BSE086007
[A50]3BSE059612Certified Correction Handling 800xA Safetyguidelineactive-OnePCP DMS 3BSE059612
[A51]3BSE043680Guideline for SW HAZOPguidelineReplaced by the corresponding document on the webpage-Guideline for HAZOP
[A52]3BSE089328User Documentation Review GuidelineguidelineactivePPT; Valid for user documentationOnePCP DMS 3BSE089328
[A53]3BSE089747Configuration Change Control in TFS (Agile)Process descriptionno more valid
(CT-QMS)
Not valid for / nor used by Functional Safety.N/A
[A54]3BSE048671Checklist Implementation of change request for hardware unitchecklistno more valid
(CT-QMS)
Only used by the AC 160 HW development. Replaced by the RU checklist.N/A
[A55]3BSE087000AutoSVT Code Review Guidelineguidelineactive-One PCP DMS 3BSE087000
[A56]3BSE090475Security Handbookhandbookno more valid
(CT-QMS)
Information is available on
Cyber Security web page
Cyber Security

() - Documents marked with '' are user manuals and not part of the QMS

All these standards are normative references. Access to the standards is restricted and is not linked here.

Ref. NoIdYearTitleDoc kindValidity in PCP R&D Processes
[B1]IEC 61508 2nd Edition2010Functional safety of electrical/electronic/programmable electronic safety-related systems (parts 1-7)standardvalid
[B2]IEC 61508-1 2nd Edition2010Part 1: General requirementsstandardvalid
[B3]IEC 61508-2 2nd Edition2010Part 2: Requirements for electrical/electronic/programmable electronic safety-related systemsstandardvalid
[B4]IEC 61508-3 2nd Edition2010Part 3: Software requirements standardstandardvalid
[B5]IEC 61508-4 2nd Edition2010Part 4: Definitions and abbreviations standardstandardvalid
[B6]IEC 61508-5 2nd Edition2010Part 5: Examples of methods for the determination of safety integrity levelsstandardvalid
[B7]IEC 61508-6 2nd Edition2010Part 6: Guidelines on the application of IEC 61508-2 and IEC 61508-3standardvalid
[B8]IEC 61508-7 2nd Edition2010Part 7: Overview of techniques and measuresstandardvalid
[B9]IEC 615112016Functional safety – Safety Instrumented systems for the process industry sectorstandardvalid
[B10]IEC 61511-12016Part 1: Framework, definitions, system, hardware and software requirementsstandardvalid
[B11]IEC 61511-22016Part 2: Guidelines for the application of IEC 61511-1standardvalid
[B12]IEC 61511-32016Part 3: Guidance for the determination of the required safety integrity levelsstandardvalid
[B13]EN ISO 13849-1:20152015Safety of machinery - Safety-related parts of control systems - Part 1: General principles for designstandardvalid
[B14]EN ISO 13849-2:20122012Safety of machinery - Safety-related parts of control systems - Part 2: Validationstandardvalid
[B15]IEC 62061:20212021Safety of machinery - Functional safety of safety-related electrical, electronic and programmable electronic control systemsstandardvalid

C) Processes

Ref. NoDocument IdTitleDoc kindValidity in PCP R&D ProcessesCommentPCP R&D Processes reference
[C1]3BSE034125Product Development, Process descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety HandbookProcess Descriptions
[C2]3BSE034124Product Development, Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookProcess Descriptions
[C3]3BSE034120Project Planning, Process descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety HandbookIntegrated Project Management
[C4]3BSE034119Project Planning, Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookIntegrated Project Management
[C5]-N/AN/Aremoved already in CT QMS-N/A
[C6]3BSE034122Project Monitoring and Control, Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookIntegrated Project Management
[C7]3BSE042926Project Closing, Process Descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety HandbookIntegrated Project Management
[C8]3BSE042925Project Closing, Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookIntegrated Project Management
[C9]3BSE044102SAM Process Descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety Handbook3rd-Party & OSS
[C10]3BSE044103SAM Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety Handbook3rd-Party & OSS
[C11]3BSE034388Risk Management Process, Descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety Handbook (PMO responsibility)
Risk management covered in OnePoint
PCPOnePoint/Risk Management
[C12]3BSE034202Risk Management Process, Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety Handbook (PMO responsibility)
Risk management covered in OnePoint
PCPOnePoint/Risk Management
[C13]3BSE033610Requirement Definition, Process Descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety Handbook; available on webpageRequirements
[C14]3BSE037710Requirements Definition Processprocess mapno more valid
(CT-QMS)
reference not used in Safety Handbook; available on webpageRequirements
[C15]-WithdrawnN/Aalready withdrawn in CT QMS-N/A
[C16]-WithdrawnN/Aalready withdrawn in CT QMS-N/A
[C17]3BSE034103Technical Solution Process, descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety HandbookProcesses
[C18]3BSE034101Technical Solution Process mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookProcesses
[C19]2PAA124050Productization Processprocess descriptionno more valid
(CT-QMS)
reference not used in Safety HandbookRelease
[C20]2PAA123665Productization Process – Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookRelease
[C21]3BSE033644Integration Process, descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety HandbookN/A
[C22]3BSE033602Integration process mapprocess mapno more valid
(CT-QMS)
reference not used in Safety HandbookN/A
[C23]3BSE034097Verification process, descriptionprocess descriptionno more valid
(CT-QMS)
reference not used in Safety Handbook.
Part of Engineering
Test
[C24]3BSE034098Verification (Product Development) Process Mapprocess mapno more valid
(CT-QMS)
reference not used in Safety Handbook.
Part of Engineering
Test
[C25]-WithdrawnN/Aalready withdrawn in CT QMS-N/A
[C26]3BSE033429Configuration Management, process mapprocess mapno more valid
(CT-QMS)
Use contents on webpageConfiguration Management
[C27]3BSE036454PPQA Process mapprocess mapno more valid
(CT-QMS)
reference not used in Safety Handbook
replaced by Quality & KPI process
Quality & KPI Process
[C28]3BSE033641Configuration Management, Process Descriptionprocess descriptionno more valid
(CT-QMS)
-Configuration Management
[C29]3BSE040876_TPFChecklist for Roll-up Projectchecklistactive-available as a template in 'Templafy'
[C30]3BUL980146Writing and Publishing Field Communicationguidelineactive-L4 & Maintenance

Owner: Functional Safety Team